OKEECHOBEE -- Septic-to-sewer projects in Okeechobee County will take thousands of homes off septic tanks and improve water quality in runoff ...
Join our family of readers for as little as $10 per month and support local, unbiased journalism.
Already have an account? Log in to continue. Otherwise, follow the link below to join.
To Our Valued Readers –
Visitors to our website will be limited to five stories per month unless they opt to subscribe.
For $5, less than 17 cents a day, subscribers will receive unlimited access to SouthCentralFloridaLife.com, including exclusive content from our newsroom.
Our commitment to balanced, fair reporting and local coverage provides insight and perspective not found anywhere else.
Your financial commitment will help to preserve the kind of honest journalism produced by our reporters and editors. We trust you agree that independent journalism is an essential component of our democracy.
Please click here to subscribe.
Sincerely,
Katrina Elsken, Editor-in-Chief, Independent Newsmedia
Please log in to continueNeed an account?Subscribe to continue reading. Get every story for $10 a month. You can cancel at anytime. Register for an accountYou'll need an account on our site to post calendar listings and comment on stories. Sign up today. It's free, and takes just a minute! |
OKEECHOBEE -- Septic-to-sewer projects in Okeechobee County will take thousands of homes off septic tanks and improve water quality in runoff that goes into Lake Okeechobee.
At the Oct. 22 meeting of the Okeechobee County Board of County Commissioners OUA Executive Director Greg Kennedy phases 1 and 2 of the Southwest septic-to-sewer project have been completed. The third phase involves running the sewer lines from SW 24th Avenue, down to 32nd, then 16th and SR 78. This line will go all the way to the Okee-Tantie.
Kennedy said one of the challenges has been obtaining a permit to drill under the Herbert Hoover Dike from the U.S. Army Corps of Engineers. “We’re in the fourth round or responding to questions,” he explained.
He said OUA will also work with Big Cedar Lodge (the resort division of Bass Pro Shops) to determine the needs for water and sewer services at Okee-Tantie. He said they have not met yet with “exact plans on the table to determine exactly what they will need.”
“We are hopeful that by 2027, we will have this (sewer project) underway and have it built in time for what the developer needs,” he said.
“We can’t control the pace that the federal government does their job,” said Kennedy.
He said in the Southwest section, sewer hookups have been completed to 60 homes with 60 more under construction. About 500 connections are planned.
The Treasure Island septic-to-sewer project design plans are nearing completion, Kennedy continued.
This project will connect nearly 2,000 homes that are currently using septic tanks to the sewer system. Based on water quality studies, this should be a great benefit to the environment, he said.
Treasure Island has a lot of homes on very small lots on the waterfront, he said. Tests have shown that nutrients from septic tanks enter the canals which flow into Lake Okeechobee.
He said tests have shown the nutrient load in that water is coming from human waste.
“This is an important project environmentally,” he said. OUA has obtained $20 million in grant funding for the project.